Resource Manager
CDB Resource Plan
This will control the resource usage between pluggable databases.
Package / Procedures
DBMS_RESOURCE_MANAGER.CREATE_CDB_PLAN DBMS_RESOURCE_MANAGER.DELETE_CDB_PLAN DBMS_RESOURCE_MANAGER.CREATE_CDB_PLAN_DIRECTIVE DBMS_RESOURCE_MANAGER.UPDATE_CDB_PLAN_DIRECTIVE DBMS_RESOURCE_MANAGER.DELETE_CDB_PLAN_DIRECTIVE
Views
DBA_CDB_RSRC_PLANS DBA_CDB_RSRC_PLAN_DIRECTIVES
Examples
BEGIN
DBMS_RESOURCE_MANAGER.clear_pending_area;
DBMS_RESOURCE_MANAGER.create_pending_area;
DBMS_RESOURCE_MANAGER.create_cdb_plan(
plan => 'example_cdb_plan',
comment => 'A test CDB resource plan');
DBMS_RESOURCE_MANAGER.create_cdb_plan_directive(
plan => 'example_cdb_plan',
pluggable_database => 'pdb1',
shares => 3,
utilization_limit => 100,
parallel_server_limit => 100);
DBMS_RESOURCE_MANAGER.create_cdb_plan_directive(
plan => 'example_cdb_plan',
pluggable_database => 'pdb2',
shares => 3,
utilization_limit => 100,
parallel_server_limit => 100);
DBMS_RESOURCE_MANAGER.validate_pending_area;
DBMS_RESOURCE_MANAGER.submit_pending_area;
END;